EnU-1
Reconstruction of part of production plant by replacement of electric motor drives of process fans and lightning of the plant - EnU-1
In 2018, cement factory in Našice implemented a project named „Reconstruction of a part of production plant by replacement of electric motor drives of process fans and lightning of the plant - EnU-1“ worth HRK 1.6 million out of which HRK 580.000,00 was financed by The Environmental Protection and Energy Efficiency Fund. Through expert supervision, electricity savings in the amount of 34.40% on electric motor drives were confirmed.